Railway board members inspected the ongoing work of the Panvel-Karjat corridor on Saturday, the work of the corridor is 46 per cent completed, as reported by a leading media company. The double-line project between the region is estimated to be completed by December 2025.
An official quoted in the report informed that the estimated budget of the project is Rs 2812 crore with a target to complete it by 2025.
According to the report, the inspections were carried out along with MRVC chairman and managing director Subhash Chand Gupta.
As the report suggests, approximately 57 hectares of private land has been used for the corridor which encompasses two rail flyovers, and three tunnels. The project also covers forest land for which permission has been issued by the chief conservator for forest in Thane in August 2022.